Warsaw, 8 May 2015
FPP informs that:
The progress of work at building B4 is estimated at 54%. The excavation is completed at 100%, drainage at 100%, reinforced concrete structure at 100%, insulation of the underground section at 100%, backfill at 100%, brickwork at 98%, roof insulation at 90%, external systems (rainwater drainage system, sewage system) at 90%, sanitary systems and ventilation at 40%, electrical systems at 50%, plasterwork at 30%, external railings at 10%, windows at 20%, the facade at 10%.