Warsaw, 21.12.2015
Dear Sir or Madam,
Progress of works in C2 buildings is estimated at 37%. The reinforced concrete structure has been completed in 99% and the insulation of the underground part of the building in 99%. The progress in masonry works is at 50%, whereas roof insulation at 3%. We have begun the installation of plumbing systems.
Sales and Marketing Department